Bathroom remodel
- 2–4 weeks active construction. Add 2–3 weeks for design + material lead time.
Kitchen remodel
- 3–6 weeks active construction. Custom cabinets add 6–10 weeks of lead time.
Basement finishing
- 6–10 weeks for 800–1,500 sq ft. Permits + inspections add 1–2 weeks.
Full home remodel
- 10–20+ weeks depending on scope and how much structural change is involved.
What slows projects down
- Custom material lead times, change orders, inspection scheduling, and homeowner decision delays.